⚡ SELAMAT DATANG DI SISTEM INFORMASI MCP WSSL 1 ⚡

Jenbacher 1

Power Listrik

14,600 kWh

Jam Operasional

24 Jam

Ganti Oli Selanjutnya

1341 Jam

08 Jul 2026
Overhaul Selanjutnya

9582 Jam

17 Jun 2027

Jenbacher 2

Power Listrik

12,600 kWh

Jam Operasional

21 Jam

Ganti Oli Selanjutnya

271 Jam

25 May 2026
Overhaul Selanjutnya

6235 Jam

28 Jan 2027
📊 Realisasi Produksi Tahun 2026 (Update terakhir: 12 May 2026)
No Item Realisasi Target Progress %
1 Ton TBS 122,821.72 450,000.00
27.3%
27.3%
2 POME 67,497.00 225,000.00
30.0%
30.0%
3 Umpan 65,560.00 182,500.00
35.9%
35.9%
4 Biogas 1,451,439.00 4,380,000.00
33.1%
33.1%
5 Listrik 2,910,800.00 9,114,903.00
31.9%
31.9%
6 Kernel 9,463.25 37,175.00
25.5%
25.5%
7 kWh / Biogas 2.04 2.15
95.1%
95.1%
8 Biogas / POME 22.14 24.00
92.2%
92.2%
📈 Produksi Biogas
⚡ Produksi & Distribusi Listrik
đŸĨ§ Alokasi Listrik

đŸŽĨ Pengenalan Lingkungan Kerja MCP
Bioreaktor
Scrubber
Engine Room MCP